Wellbrook by Azure - Construction Update October 2026

We hope you enjoy the latest construction update for Wellbrook by Azure.

Welcome to the October construction update for Wellbrook by Azure. We’re pleased to share the latest progress across the community as work continues to advance across the residences, communal amenities and external works.

A key milestone this month is the connection of power to approximately half of the residences, with commissioning now underway. Landscaping along Anzac Avenue and Buchanan Street has also been completed, while asphalt preparation works continue across the community.

Across Terraces 1 to 48, construction is progressing through the final stages, with joinery, flooring, fit-off works, landscaping, final cleaning and quality reviews either complete or well advanced. Terraces 49 to 89 have achieved lock-up, marking another important milestone as these homes continue moving towards the next phase of construction.

Further throughout the community, Terraces 90 to 131 are progressing through fit-off, joinery, rear fencing, shower screen and wardrobe installation, with final finishing works underway. Terraces 132 to 189 continue to advance through painting, tiling, cladding and internal finishes.

Across Terraces 190 to 226, roofing, framing, services and cladding works are progressing well, while Terraces 227 to 240 have been cleared and prepared for construction to commence.

Within the communal area, internal plasterboard and painting works have been completed, the sauna has been installed, and pool tiling and landscaping continue to progress. Externally, column painting and the Buchanan Street verge landscaping are complete, and landscaping works continue along Stubbins Street.

Thank you for following the progress of Wellbrook by Azure. We look forward to sharing further updates as the community continues to take shape.