Munro by Azure - Construction Update June 2025
.jpg)
We hope you enjoy the last construction update for Munro by Azure.
Welcome to the June construction update for Munro by Azure in Bundamba.
We're pleased to report steady progress on site, with significant milestones now reached across both stages of the development.
Stage 1, which includes Terraces 1 through 50, is now fully completed—marking a significant achievement for our in-house construction team and bringing us one step closer to welcoming our first residents.
In Stage 2, we’ve also made strong headway. Roofing, carpentry, stair installation, garage doors, external rendering, and tiling are now complete across all remaining terraces from 51 to 100.
Painting has been completed throughout, with the exception of Terraces 95 to 100. Carpets are now installed in Terraces 59 to 70 and 73 to 88, while joinery has been finalised in Terraces 51 to 88.
External works are also progressing well, with footpaths, driveways, and landscaping now completed for Terraces 51 to 70.
Looking ahead, upcoming works include the completion of carpets in Terraces 51 to 58, 71 to 72, and 89 to 100, as well as painting in the final group of Terraces 95 to 100.
Joinery will continue through Terraces 89 to 100, and the external works program—including driveways, footpaths, and landscaping—will move through Terraces 71 to 100.
We look forward to bringing you further updates as we move closer to completion.