Ember by Azure - Construction Update October 2026

We hope you enjoy the latest construction update for Ember by Azure.
Welcome to the October construction update for Ember by Azure.
Construction is continuing to advance across the community, with all roofing, flashings and parapet works now complete, marking the transition into the final stages of delivery. External rendering, painting and cladding works are progressing across Terraces 43 to 52 and 58-66, while internal fit-out activities are now concentrated on the final homes within Terraces 63 to 66.
Inside the homes, painting has been completed throughout Terraces 1 to 42 and is progressing through the remaining terraces. Tiling is now largely finished across the development, with only the final homes in Terraces 53-57 and 63-66 nearing completion. Joinery installation has also been completed throughout most of the community, with the remaining homes scheduled for installation shortly.
Services fit-off continues to gain momentum, with plumbing, electrical and mechanical trades working through the homes as they move closer to completion. Quality assurance checks have also started representing another significant milestone for the project.
Across the wider community, fencing and landscaping works continue to progress, while tiling within the community open space is well underway. Looking ahead, work will focus on completing the communal area with tiling to continue through November, and ongoing works to the entry stairs and gate house.
We look forward to sharing further progress as Ember continues to move closer to completion.