Ember by Azure - Construction Update May 2025

We hope you enjoy the latest construction update for Ember by Azure.

Welcome to the May construction update for Ember by Azure in Augustine Heights. We're excited to share the latest progress made throughout the month.

Earthworks are now 90% complete, setting a strong foundation for the next stage of construction. Concrete sleeper retaining walls are currently underway, alongside the footings and blockwork for the block retaining walls, which are progressing well.

Temporary power has been successfully installed to support ongoing works, while the site’s temporary water supply is also being established. Additionally, the application for the Pad-Mounted Transformer has been lodged with Energex, marking another important milestone in delivering essential infrastructure to the community.

We look forward to bringing you more updates as the Ember community comes to life.