Elwood by Azure - Construction Update June 2025

We hope you enjoy the latest construction update for Elwood by Azure.

Welcome to the June construction update for Elwood by Azure in Mango Hill. We're excited to share the latest progress made throughout the month.

Across Terraces 1 to 8, cladding is now 90% complete, with rendering and painting scheduled to commence in early July. Internal sheeting and waterproofing are both finished, and the carpentry fix-out is currently underway.

In Terraces 9 to 14, framing and roofing have been completed, while window installation and builder’s wrap are progressing well.

Terraces 21 to 26 have seen excellent progress, with scaffolding now removed, external painting finished, and internal floor finishes 90% complete. These terraces are now ready for joinery installation, which will begin in July.

In Terraces 27 to 32, external cladding is now underway. Terraces 33 to 40 are nearing the next phase, with external painting 90% complete and the scaffold scheduled to come down in early July. Internally, sheeting has reached 60% completion.

Over in Terraces 41 to 48, scaffolding has already been removed, the internal carpentry fix-out is complete, and floor finishes have commenced.

In Terraces 49 to 54 and 55 to 62, internal floor finishes are complete, and joinery installation is underway. Terraces 63 to 68 are also progressing well, with external cladding 90% complete, internal sheeting at 90%, and rendering and painting about to begin.

Within the communal area, the bin store and pump room structures are complete, with painting and rendering scheduled to start in July. Planter boxes are also being prepared for installation to Terraces 15 to 26 and 41 to 54.

We're pleased to see strong momentum across the site and look forward to sharing more updates as Elwood by Azure continues to take shape.