Dahlia by Azure - Construction Update June 2025

We hope you enjoy the latest construction update for Dahlia by Azure.

Welcome to the June construction update for Dahlia by Azure in Flinders View. We're excited to share the latest progress made throughout the month.

Retaining walls remain at 95% complete, while screw piers have reached 99% completion site-wide.

Plumbing and electrical underslab works are now finished across 13 of the 15 buildings. The subgrade road box is 75% complete, supporting continued site access and infrastructure works. Concrete slabs have been poured to Terraces 92 through 111, and perimeter scaffolding has been erected around Terraces 1–14, 53–72, and 112–129.

Timber framing has been completed for Terraces 1–10, 11–14, 53–62, 63–72, and 112–129. Upper framing is progressing across Terraces 47–52, and roof trusses are being installed on Terraces 21–28.

Roofing is now complete for Terraces 11–14, 63–72, and 112–129. Insulation has also been finalised in several of these buildings, including Terraces 1–10, 63–72, and 112–129.

A key highlight this month is the commencement of plasterboard sheeting and cladding, now underway in Terraces 112–129.

Finishing trades have now begun within the first building—an important milestone as the project continues to gain momentum.

We look forward to sharing more developments as the Dahlia community comes to life.